(1)為使环氧地坪漆塗料的施工達到良好的效果,對於尚未找平的地面,應首先施工水泥找平層以進行找平處理。土建方找平時,在水泥初凝時,用專業地面機械對地面進行磨平處理。經過基層處理再塗裝的环氧地坪漆的表面會更平整、光亮,使用壽命也會提高。
(1) In order to achieve good results in the construction of epoxy floor paint, cement leveling layer should be first applied to leveling the ground that has not yet been leveled. When constructing the cement, the civil engineers usually use the professional ground machinery to grind the ground. The surface of epoxy floor paint after base treatment and re-coating will be smoother and brighter, and its service life will also be improved.
(2)待水泥層幹燥後(大約28天),用打磨機對地面進行整體打磨處理,使其表面平整,水泥毛細孔全部敞開。
(2) After the cement layer is dried (about 28 days), the whole ground is polished with a grinder to make the surface smooth and the cement capillary holes open.
(3)對於有油污(食用油、機油)的基層,先用表面處理劑噴灑於用水沖濕的地表面,反復擦洗,直到無油污為止。如何控制环氧地坪漆塗料施工質量
(3) For the base layer with oil contamination (edible oil, engine oil), the surface treatment agent is sprayed on the surface wetted with water and scrubbed repeatedly until there is no oil contamination. How to control construction quality of floor paint
(4)對於堿性太大(PH>8)的基層,先用稀鹽酸或者稀醋酸進行中和處理,然後用清水沖洗。
(4) For the base layer with too high alkalinity (PH > 8), neutralize it with dilute hydroc彩色沥清地坪hloric acid or acetic acid, then rinse it with clean water.
(5)對於潮濕地面,通過吸水、擦幹,太陽、燈照,熱風機吹烘,使其含水率達到施工要求。
(5) For wet ground, the water content can reach the construction requirement by absorbing water, drying, sunshine, lamp illumination and hot air blower.
(6)對於有舊漆膜的地面(如金剛砂环氧地坪、舊漆膜地面),先用機械鏟除舊油漆,然後對局部不良情況進行處理,同時對地面打毛,以清除不牢固的舊水泥層及金剛砂表面,並且形成粗毛面,從而提高新塗層的附著力。
(6) For the surface with old paint film (such as diamond floor and old paint film floor), the old paint is first removed mechanically, and then the透水地坪 local bad conditions are treated. At the same time, the ground is groomed to remove the unstable old cement layer and diamond surface, and form rough surface, so as to improve the adhesion of the new coating.
(7)對於較深的伸縮縫,須先用彩色彈性膠填充到低於地平面約1~2mm的高度,然後用快幹硬油漆膩子刮平;對於已填瞭瀝青的伸縮縫,要將縫中的瀝青鏟平到低於地平面1~2mm的深度,然後用快幹硬油漆膩子刮平,防止返色。
(7) For deep expansion joints, it is necessary to fill them with colour elastic glue at a height of about 1-2 mm below the ground surface, and then scrape them with quick-drying hard paint putty; for those expansion joints filled with asphalt, the asphalt in the joints should be flattened to a depth of 1-2 mm below the ground surface, and then scraped with quick-drying hard paint putty to prevent discoloration.