工廠車間环氧地坪漆具體施工工序和流程

文章时间:2018-11-03 22:41:18   浏览次数:1138

常規环氧地坪漆施工工序:1、地面打磨清理幹凈,無塵打磨機打磨;2、塗刷高效环氧地坪漆底漆,根據不同的地面做不同的环氧地坪漆底漆,地面情況不同,环氧地坪漆底漆耗漆量也不一樣,新地面环氧地坪漆耗漆量通常是0.15kg/㎡左右,起砂嚴重的地面环氧地坪漆耗量則可達 0.5kg/㎡以上;3、环氧地坪漆底漆固化之後,塗刷無溶劑环氧环氧地坪漆中塗,根據地面环氧环氧地坪漆塗刷道數,每平米环氧地坪漆耗漆量 0.3kg/㎡;
Conventional construction procedures of epoxy floor paint: 1. Clean up the ground and polish with dust-free grinder; 2. Paint high-efficiency epoxy floor paint primer, make different epoxy floor paint primers according to different ground conditions, the amount of epoxy floor paint primer consumption is different, the amount of new ground epoxy floor paint consumption is usually 0.1. The consumption of epoxy flooring paint with serious sand rising can reach 0.5kg/or above at 5kg/. 3. After curing, epoxy flooring paint is coated with solvent-free epoxy flooring paint. According to the number of brushing paths of epoxy flooring paint, the consumption of epoxy flooring paint is 0.3kg/per square meter.
4、塗刷环氧膩子,用於填補細縫,环氧地坪漆耗漆量 0.2kg/㎡;
4. Apply epoxy putty to fill the seam. The paint consumption of epoxy floor paint is 0.2kg/.
5、刮塗兩遍环氧地坪漆面漆,环氧地坪漆耗漆量 0.3kg/㎡,自流平面漆是先刮塗一道环氧地坪漆,然後再鏝塗一道环氧地坪漆,耗漆量為 1.1kg/㎡;
5. Scrape two times of epoxy floor paint, the consumption of epoxy floor paint is 0.3 kg/. Self-flow floor paint is to scra透水地坪pe an epoxy floor paint first, then apply an epoxy floor paint, the consumption of paint is 1.1 kg/.
6、為瞭更好的防止环氧地坪磨損漆膜破損,可以在塗刷环氧地坪漆面漆後,固化之後再塗刷一道清漆环氧地坪漆自流平,這樣更好的防止环氧地坪漆漆膜長久摩擦破損,有效的延長瞭地坪的使用壽命。
6. In order to prevent the wear and tear of epoxy flooring paint film, one can apply a varnish epoxy flooring paint to self-leveling after painting the epoxy flooring paint, which can better prevent the long-term friction and tear of the epoxy flooring paint film and effectively prolong the service life of the flooring.

环氧地坪鋪裝設基本流程
Basic process of epoxy floor paving
(0) 面塗批補:采用面塗材料配石英細粉批塗,填補中塗較大顆粒間的空隙,待完全固化後,用無塵打磨機打磨地面,用吸 塵器吸盡灰塵、打磨平整。
(0) Surface painting batch repairing: using surface coating material with quartz powder batch coating, filling the gap between larger particles in the middle coating, to be fully solidified, using dust-free grinder to grind the ground, using a vacuum cleaner to absorb dust, grinding flat.
(1) 基層處理:打磨掉松散層、脫層及水泥殘渣,使之堅硬、平整,並增加地坪塗層與地面的附著力。
(1) Base treatment: grinding loose layer, delamination and cement residue to make it hard and smooth, and increase the adhesion between the floor coating and the ground.
(2) 底塗施工:把环氧封閉底漆配好後,輥塗、刮塗或刷塗,使其充分潤濕混凝土,並滲入到混凝土內層。
(2) Primer construction: After the epoxy sealing primer is matched, roll, scrape or brush are applied to wet the concrete fully and infiltrate into the inner layer of the concrete.
(3) 中塗施工:將中塗材料與適量的石英砂充分混合攪拌均勻,用鏝刀鏝塗成一定厚度的平整密實層。
(3) Intermediate coating construction: mix the middle coating material with appropriate amount of quartz sand and mix evenly, and coat it with trowel to form a uniform and compact layer with a certain thickness.
(4) 面塗批補:采用面塗材料配石英細粉批塗,填補中塗較大顆粒間的空隙,待完全固化後,用無塵打磨機打磨地面,用吸 塵器吸盡灰塵、打磨平整。
(4) Surface painting batch repairing: using surface coating material with quartz powder batch coating, filling the gap between the larger particles in the middle coating, to be fully solidified, using dust-free grinder to grind the ground, using a vacuum cleaner to absorb dust, grinding flat.
(5) 面塗施工:將环氧色漆及固化劑混合均勻後,可鏝塗、刷塗、輥塗或噴塗,使其流平,獲得平整均勻的表面塗層。
(5) Surface coating construction: After mixing epoxy paint and curing agent evenly, it can be sprayed, brushed, rolled or sprayed to make it level and obtain a smooth and uniform surface coating.

工廠車間环氧地坪漆施工步驟:
Plant floor epoxy floor paint construction steps:
1、基面清理:用機動打磨機磨粗基面的同時,再用手動打磨機清除需要徹底清理的基面;
1. Base surface cleaning: While grinding rough basement surface with a motor grinder, then using a manual grinder to remove the basement that needs to be thoroughly cleaned;
2、清潔、檢查基底:對基面吸塵幹凈後,檢查基底有無裂縫、空殼,如有,則須深層切割清理後用环氧樹脂砂漿填補,由於环氧樹脂不容水,所以在處理過程中隻能進行幹處理,清理時不可野蠻敲打,以免敲松邊上的基層。
2. Clean and check the base: After cleaning the base surface, check whether there are cracks and empty shells in the base. If so, it must be cut deep and filled with epoxy resin mortar. Because the epoxy resin is not water-tolerant, it can only be dry treated in the process of cleaning, so it can not be brutally knocked when cleaning, so as to avoid loosening the base on the edge.
3、环氧樹脂底漆塗裝:在進行基底處理的同時,可進行环氧底塗 塗裝,施工配料時要註意施工進度與用料的平衡,不可一次開料過多,保證材料在塗裝時仍符合可使用時間,在膠化前被塗刷完,讓材料保持良好的滲透性,保證粘接性能;
3. Epoxy resin primer coating: epoxy primer coating can be carried out at the same time as the base treatment. The balance between construction progress and materials should be paid attention to during construction proportioning, so as to ensure that the material s彩色沥清地坪till meets the usable time in painting and is painted before gelatinization, so as to maintain good permeability of the material, and ensure that the material can not be overloaded at one time. Adhesive property;
4、在底塗固化後,首先用环氧樹脂中塗配石英砂鏝刮环氧石英砂漿N遍,以增加整個漆膜的厚度加強漆膜的抗壓、抗沖擊等物理性能;
4. After solidification of the primer, the epoxy resin is first coated with quartz sand to scrape the epoxy quartz mortar N times, so as to increase the thickness of the whole film and enhance the physical properties of the film, such as compression and impact resistance.
5、环氧樹脂批土中塗:砂漿層固化後,再刮环氧批土2道,封閉砂眼和氣孔,打磨膩子並吸塵幹凈。
5. Epoxy resin batch soil coating: after curing the mortar layer, scrape the epoxy batch soil 2 ways, seal sand holes and stomata, Polish putty and dust clean.
6、环氧樹脂面塗塗裝:打磨中塗層,在確保基面被完全封閉的情況下,按設計要求施工环氧樹脂平塗面塗2道,施工時將面塗材料攪拌均勻後滾塗施工;塗裝施工的环境要求:施工基面應保持幹凈、幹燥,無其他工程施工交叉作業,室內空氣相對濕度宜小於85%,當濕度過大時應停止施工;
6. Epoxy resin surface coating: coating in polishing, in order to ensure that the base surface is completely closed, two epoxy resin flat coatings should be constructed according to the design requirements, and the surface coating materials should be stirred evenly before rolling coating construction; the environmental requirements of coating construction: the construction base surface should be kept clean and dry, and there is no cross-work of other engineering construction. Industry, indoor air relative humidity should be less than 85%, when humidity is too large, we should stop construction.
7、現場清理維護、地坪養護:面塗完成後將有關施工材料、工具搬離現場,嚴密封閉保護完成飾面,至少48小時後才可允許人進入行走。並不可帶進泥沙,漆膜完全固化一般需7天時間,期間應避免進行其他工程施工、搬運、安裝等施工。
7. On-site cleaning and maintenance, floor maintenance: After finishing the surface painting, the relevant construction materials and tools will be removed from the site, and the finish decoration will be tightly sealed and protected. At least 48 hours later, people can be allowed to walk. No sediment should be brought in. It usually takes 7 days to solidify the paint film completely. During this period, other engineering construction, handling and installation should be avoided.