环氧防靜電地坪必須在什麼條件下施工
想讓环氧防靜電地坪達到最佳的效果,那麼必須要先滿足其施工條件才能做到事辦功倍的效果,下面濟南華彩环氧地坪就來為您仔細瞭解下环氧防靜電地坪施工條件要求:
In order to achieve the best effect of epoxy anti-static floor, it is necessary to meet its construction conditions in order to achieve twice the effect of success. The following Jinan Huacai floor for you to carefully understand the requirements of epoxy anti-static floor construction conditions:
1、現場和氣候:
1, the scene and climate:
現場:要求封閉施工現場,無交叉作業,施工照明良好;
Site: requires closed construction site, no cross operation, good construction lighting.
氣候:空氣相對溫度要求〈75%,地面溫度高於露點溫度3℃以上。
Climate: air relative temperature requirement 75%. Surface temperature is higher than dew point temperature above 环氧地坪3 degrees Celsius.
2、基層:含水率和pH值(基層的含水率小於4%;pH值 小於9)。
2, grass-roots level: moisture content and pH value (moisture content of grass roots is less than 4%; pH value is less than 9).
防靜電环氧地坪
Antistatic Epoxy Floor
3、人員和施工管理:
3. Personnel and construction management:
施工人員:施工人員應有一定的施工經驗,主要工種人員應技術熟練;
Construction personnel: the construction personnel should have certain construction experience, and the main type of workers should be skilled.
施工人員的管理:施工人員要組織得當,分工協作合理,銜接流暢,現場指揮人員應富有印花地坪經驗。
Construction personnel management: construction personnel should be properly organized, reasonable division of labor and cooperation, smooth connection, site commanders should be experienced.
4、勞動保護措施:
4, labor protection measures:
防火安全:施工現場要註意防火和用電安全,安排專人佈線掌燈;
Fire safety: attention should be paid to fire safety and electricity safety at the construction site.
勞動保護:施工人員應穿工作服、戴手套、穿勞保鞋,進入施工區換穿拖鞋或穿鞋套。
Labor protection: construction personnel should wear work clothes, gloves, wear labor protection shoes, into the construction area to wear slippers or shoes.
5、機具和儀器準備:
5, machinery and equipment preparation:
機具:要準備好施工專用機具,如攪拌機、吸塵器、拖佈,打料槍、推車、料桶、齒刀、刮板、針輥筒、釘鞋、鞋套、手套、加長桿、紙膠帶、開桶器、批刀、鏟刀等,放置於現場,隨用隨取;
Tools: Prepare special construction equipment, such as mixer, vacuum cleaner, mop, shotgun, trolley, barrel, toothed knife, scraper, needle roller, nail shoe, shoe cover, glove, lengthening rod, paper adhesive tape, barrel opener, batch knife, shovel, etc., and put them on the spot as needed.
儀器:計量儀器如電子秤、溫度計、溫濕度儀、地溫表、卷尺、靠尺和電阻儀等要備於現場,隨時測量。塗層的厚度主要靠控制塗料的用量進行保證,施工時應隨時記錄溫度和濕度。
Instruments: Measuring instruments such as electronic scales, thermometers, temperature and humidity meters, ground temperature meters, tapes, rulers and resistors to be ready on the spot, at any time to measure. The thickness of the coating is mainly guaranteed by controlling the dosage of the coating. The temperature and humidity should be recorded at any time during the construction.