环氧地坪施工流程步驟有哪些?

文章时间:2019-02-19 00:29:51   浏览次数:1454

环氧地坪施工流程步驟1、环氧地坪施工流程步驟之基面清理:用機動打磨機進行磨粗基面的同時,需要再用手動打磨機清除需要徹底清理的基面。2、环氧地坪施工流程步驟之清潔及檢查基底:當對基面吸塵幹凈後應檢查基底有無裂縫、空殼,若是有則須深層切割清理後用环氧樹脂砂漿填補,還有由於环氧樹脂不容水,因而在處理過程中隻能進行幹處理,清理時不可野蠻敲打二以免敲松邊上的基層。
Epoxy flooring construction process step 1, epoxy flooring construction process step of the base surface cleaning: while using a mobile grinder to grind rough base surface, it is necessary to use a manual grinder to remove the need for thorough cleaning of the base. 2. Cleaning of the construction process of epoxy flooring and checking the base: When the base surface is cleaned up, check whether there are cracks and empty shells in the base. If so, deep cutting and cleaning should be done to fill the base with epoxy mortar. Because the epoxy resin is not water-tolerant, only dry treatment can be carried out in the process of treatment, and brutal knocking can not be done to avoid loosening the base on the edge.
3、环氧地坪施工流程步驟之环氧樹脂底漆塗裝:在進行基底的處理同時,可進行环氧底塗與塗裝,施工配料時要施工進度與用料的平衡需把握,不可一次開料過多,保證材料在塗裝時仍符合可使用時間,在膠化前被塗刷完,讓材料保持良好的滲透性,保證粘接性能。
3. Epoxy resin primer painting in the construction process of epoxy flooring: epoxy primer and coating can be carried out at the same time of the treatment of the base. The balance between construction progress and materials should be grasped when the construction ingredients are used. It is not necessary to open too much material at one time, so as to ensure that the material still meets the usable time in painting and is painted before cementing, so that the material can maintain good permeability and bonding performance. 。
4、环氧地坪施工流程步驟之在底塗固化後:先用环氧樹脂中塗配石英砂鏝刮环氧石英砂漿N遍,以增加整個漆膜的厚度加強漆膜的抗壓、抗沖擊等物理性能。
4. After the curing of the epoxy floor construction process, the epoxy resin is first coated with quartz sand to scrape the epoxy quartz mortar N times, so as to increase the thickness of the whole film and strengthen the physical properties of the film, such as compression and impact resistance.
5、环氧环氧地坪施工流程步驟之之环氧樹脂批土中塗:砂漿層固化後,再刮环氧批土2道,封閉砂眼和氣孔,打磨膩子並吸塵幹凈。
5. Epoxy resin batch soil coating in the construction process of epoxy flooring: after curing the mortar layer, scrape the epoxy batch soil twice, seal sand holes and air 印花地坪holes, Polish putty and clean the dust.
6、环氧环氧地坪施工流程步驟之环氧樹脂面塗塗裝:打磨中塗層,在確保基面被完全封閉的情況下,按設計要求施工环氧樹脂平塗面塗2道。
6. Epoxy resin surface coating in the construction process of epoxy flooring: coating in polishing, two epoxy flat coatings are applied according to the design requirements under the condition that the环氧地坪 base surface is completely closed.
7、环氧地坪施工流程步驟之現場清理維護、地坪養護:面塗完成後將有關施工材料、工具搬離現場,嚴密封閉保護完成飾面,至少48個時辰後才可允許人進入行走。
7. On-site cleaning, maintenance and maintenance of epoxy flooring construction process steps: after finishing the surface coating, the relevant construction materials and tools are removed from the site, and the finishing is tightly sealed and protected. Only after 48 hours can people be allowed to walk.