熱風爐檢修前需要做哪些準備工作
1.確定熱風爐檢修類別:根據熱風爐歷年的運行和修理資料,設備安全狀況,設備缺陷,機械磨損記錄,結合本企業的生產情況,確定熱風爐檢修類別,作出熱風爐計劃修理的安排。2.作好技術準備:按照熱風爐檢修類別的標準項目和在這次檢修中需要改進的設備和項目,根據質量標準的技術要求,作好圖紙資料,工藝施工的技術準備工作。同時提出原料、印花地坪備件、工具計劃、作好物質準備。
1. Determine the type of hot-blast stove maintenance: According to the operation and repair data of hot-blast stove over the years, equipment safety status, equipment defects, mechanical wear records, combined with the production situation of the enterprise, determine the type of hot-blast stove maintenance, make the arrangement of hot-blast stove planned repair. 2. Make technical preparation: According to the standard items of hot blast stove maintenance category and the equipment and projects that need to be improved in this maintenance, and according to the technical requirements of quality standards, make technical preparation for drawing materials and process construction. At the same time, the plan of raw materials, spare parts, tools and material preparation are put forward.
3.停爐檢查:按計劃把熱風爐停下來,對熱風爐進行內外部的詳細檢驗,校對熱風爐圖紙是否與其實際情況相符,評價設備的技術狀況,修改和補充標準項目的內容,並據以進一步修改和充分材料、備件、工具。
3. Stop checking: Stop the hot stove according to plan, check the inside and outside of the hot stove in detail, check whether the drawing of the hot stove conforms to the actual situation, evaluate the technical status of the equipment, modify and supplement the contents of the standard items, and further modify and adequately modify the materials, spare parts and tools accordingly.
4.確定各種修理定額:如確定大,中,小修的勞動量定額和設備修理的停歇時間定額,作好經濟預算等。
4. Determine various repair quotas: for example, determine the labor quota for large, medium and small repairs and the stop time quota for equipment repairs, and make a good economic budget, etc.
5.安排施工:制定安全措施,編制進度表,指定專人負責,組織施工力量,配備現場技術指導和質量檢驗。在施工過程中,嚴格按質量標準執行自檢、互查、專職檢驗的“三檢制”,對各項工作進行考核,開展全面質量管理,提高檢修質量。
5. Arrange环氧地坪ment of construction: formulation of safety measures, preparation of schedule, appointment of special personnel responsible for, organization of construction force, equipped with on-site technical guidance and quality inspection. In the process of construction, the "three inspection systems" of self-inspection, mutual inspection and full-time inspection are strictly carried out according to the quality standards. The work is assessed, the total quality management is carried out, and the quality of maintenance is improved.